LADWP electric crews have been working 16 hour shifts, 7 days a week, to safely restore electric service to the Pacific Palisades area, focusing their efforts on areas with the least damage to power distribution infrastructure.

Crews have made tremendous progress to complete temporary repairs, restoring power to nearly all homes and businesses in the Pacific Palisades area that are able to safely receive power.

Operations Command Center for Pacific Palisades Power Restoration Efforts

Areas of Completion

as of February 11, 2025

Power Poles

Removed approximately 700 burned and destroyed poles

Cable

Installed more than 50,000 feet of new 4.8 KV cable

Wire

Replaced more than 2,000 feet of secondary wire

Our Dedication

LADWP crews continue to complete more complex temporary repairs to continue connecting individual customers to circuits that have been restored. The power restoration to customers in areas around the heaviest burned area will continue to be the biggest challenge moving forward.

We are committed to supporting our customers and the community through the recovery and will continue working every day to until to support the rebuilding effort in the Pacific Palisades.

Power Crew for Pacific Palisades Power Restoration Efforts
Windstorm Response for Pacific Palisades Power Restoration Efforts
Power Restoration Efforts for UUROC crew on pole
Power Reconstruction for Pacific Palisades Power Restoration Efforts

If you are within the Palisades fire burn scar and do not have power, please call us at